| Key Data |
| Order Year | 2003–2004, phase II early 2008 |
| Project Type | New plant (Refurbished building) |
| Location | Bloomington, Indiana, US |
| Estimated Investment | $70m (phase two $80m and starting in mid 2008) |
| Completion | 2005–2006 (manufacture started in third quarter of 2006 following completion of validation), Phase two complete by 2010 |
| Key Players |
| Sponsors | Cook Pharmica, Bloomington Economic Development Corporation, BioCrossroads, Indiana Health Industries Forum, Bloomington Life Sciences Partnership, local and state government agencies, Purdue University, Indiana University, |
| | Indiana Economic Development Corporation |
| Financing | Cook Pharmica, Bloomington Economic Development Corporation, BioCrossroads, Indiana Health Industries Forum, Bloomington Life Sciences Partnership, local and state government agencies, Indiana Economic Development Corporation |
| Architect | GS Ridgway & Associates Inc |
| Contractors | Silver Creek Engineering Inc, RL Turner Corp, Building Associates Inc, Project Planning & Delivery Inc, Clark, Richardson and Biskup (CRB), Commissioning Agents, Inc., AES Clean Technology Inc, Mussett Nichols and Associates (MNA), |
| | Harry J Kloeppel and Associates, Harrell-fish Inc (HFI), Cassady Electrical Contractors Inc, Trane, Spriax/UltraPure, Cummins Inc, the Rovisys Company Inc (Emerson Delta V), ESC, Cleaver-Brooks Inc, YORK, Baltimore Air Coil (BAC), ABEC And Wave Biotech, |
| | Westfalia Separator, IPEC, Millipore, Pall Corporation, Mueller and DCI, Cornerstone Flooring and Linings and Siemens Building Technologies Inc |